Ashland Pond is open again — for now

Chance Metcalf, project manager of the outflow relocation project, looks out at the rapidly refilling Ashland Pond Thursday Ashland.news photo by Morgan Rothborne
September 19, 2023

Popular city-owned 22-acre open space beloved as dog walking, bird watching retreat has been construction zone for nearly 14 months

By Morgan Rothborne, Ashland.news

A year-plus project at Ashland Pond is almost done and the area is open again for residents — until the weather cools enough to finish the final details of a multi-million dollar Public Works construction project.

Chance Metcalf, project manager of the wastewater treatment plant outflow relocation project with city of Ashland Public Works, walked behind a chain link fence dividing the entrance to the project area from the rest of the wastewater treatment plant Thursday morning. 

“I know a lot of people think it’s a pond project, but it’s not,” he said as he walked over a pathway on a long straight mound of bare ground and weeds. 

Under the mound is the project — a new pipe that will reroute the plant’s outfall of treated effluent water from Ashland Creek into Bear Creek. In order to create the new system, Ashland Pond had to be drained to build the pipe’s outfall structure and trails were closed for construction, Metcalf said. In the coming months, the new system will undergo a series of tests and, if they are successful, the effluent will be permanently rerouted through the new pipe. 

Chance Metcalf, project manager of the outflow relocation project, points out aspects of the wastewater outflow relocation project. Ashland.news photo by Morgan Rothborne

Once the weather cools, the path will be seeded with grass. Other aspects of the project are waiting on the weather too. Some of the heavy machinery isn’t safe to run until fire season is over, he said as he walked closer to where the scars of the Almeda Fire are still visible in the area. Some of this work may close the 22.05 acre open space area again in the coming months, but not for long, he said. 

The project was presented to Ashland City Council by then project manager Kaylea Kathol and Public Works Director Scott Fleury on May 23, 2022. Ashland’s Wastewater Treatment Plant needed to relocate the pipe to bring the wastewater plant into compliance with state and federal water quality regulations, according to meeting materials. 

Ashland Creek is too shallow and the water moves too slowly to accommodate the outflow of the recently processed, significantly warmer effluent water from the plant. The temperature difference was outside the standards set by the DEQ to protect the fish and ecology of the Bear Creek basin. Ashland City Council voted to approve the project to divert the outflow to deeper and faster moving Bear Creek through a new underground pipe, according to the meeting materials.

The wastewater outfall route was selected, in part, for its avoidance of the heavily used Bear Creek Greenway Trail, elimimating crossing of Ashland Creek, and for the minimal impact to sensitive habitat, according to the city. City of Ashland graphic

Now, a year later, the project is nearing completion. In response to questions about the water level of Ashland Pond, Metcalf pointed to the rising water levels as the project nears completion. Though the pond is now refilling, it may take time to return to prior levels. 

Metcalf said he does not know the history of the pond, but he had been told it originally filled extremely slowly. (The pond was originally excavated as a quarry for a local road project in the late 1960s.) While the pond does have water rights to Ashland Creek, it will be hard to know if the flow of the creek will be enough to fill the pond without the additional water from the outflow pipe. 

Trees still showing the burn scars of the Almeda Fire at Ashland Pond. Ashland.news photo by Morgan Rothborne

“We’re looking at all kinds of options, but we can’t really tell until the wet season what’s going to happen. … We won’t wait, we’ll find another option,” he said of refilling Ashland Pond. 

Metcalf couldn’t speak to the potential environmental impacts of the period of low water levels for the pond, but on Thursday, ducks swam over its surface and birds sang from the nearby vegetation. 

Several details of the project were chosen with the local ecology in mind. The outfall structure is designed to prevent fish from venturing into where the warmth of the effluent water could harm them. The project also includes a dedicated flow meter to more accurately measure that the effluent is meeting the DEQ’s National Pollutant Discharge Elimination System Permit, he said. 

The flow meter and an unexpectedly difficult excavation process led to additional costs for the project, he said. The original estimate was $3.6 million, but the final cost was $3.8 million. The project is expected to be completed sometime this fall, Metcalf said. 

For more information on the project or to be added to an email list for project updates, send an email to the city Public Works Department at [email protected].

Email Ashland.news reporter Morgan Rothborne at [email protected].

Construction equipment at Ashland Pond on Thursday. Ashland.news photo by Morgan Rothborne
Picture of Bert Etling

Bert Etling

Bert Etling is the executive editor of Ashland.news. Email him at [email protected].

Related Posts...

Our Sponsors

Ashland Community Composting Ashland Oregon

Latest posts

Residents, vendors voice concerns about Ashland farmers market

Once a vibrant hub for local produce and community gathering, the Ashland Growers Market is now, some say, struggling with shrinking sales and dwindling attendance. Longtime vendors report drops of up to two-thirds in revenue, while people voice frustrations over pricing, location and atmosphere.

Read More >

Our Sponsors

Conscious Design Build Ashland Oregon
Ashland.news Classifieds Ashland Talent Phoenix Medford Oregon
Ashland Climate Collaborative Sreets for Everyone Ashland Oregon
Ashland.news Wildfre Preparedness Guide Fire Edition Southern Oregon

Explore More...

This year’s Ashland Mystery Festival is scheduled to run Oct. 16 through 19, and will be headquartered at the Historic Ashland Armory.
Throughout October, 12 female professionals from across the country and Australia — organized by Ashland-based nonprofit Keeping All Women Safe (KAWS) — will offer “valuable information” to help women and men cultivate safer, healthier and more empowering lives and relationships.
The Oregon Senate on Monday passed the long-awaited transportation bill to update the state's funding sources for road maintenance and operations. The bill would raise taxes and fees, including a gas tax increase from $0.40 to $0.46, effective Jan. 1, 2026.
Once a vibrant hub for local produce and community gathering, the Ashland Growers Market is now, some say, struggling with shrinking sales and dwindling attendance. Longtime vendors report drops of up to two-thirds in revenue, while people voice frustrations over pricing, location and atmosphere.
Just over a dozen community members, volunteers and those with lived experience of homelessness gathered at the Bear Creek Social Center in Talent for a 90-minute workshop and open discussion on de-escalation, trauma  and homelessness on Wednesday, Sept. 24. 
ashland.news logo

Subscribe to the newsletter and get local news sent directly to your inbox.

(It’s free)

Don't Miss Our Top Stories

Get our newsletter delivered to your inbox three times a week.
It’s FREE and you can cancel anytime.