Medella Bison Ranch solar installation approved by county hearing officer

A photo from the mtsolar.us website shows a type of pole-mounted solar panels similar to those proposed for installation on the Medella Bison Ranch on the east side of Highway 99 (North Main Street) just north of the Ashland city limit.
January 14, 2026

County approval clears way for pole-mounted solar arrays on land zoned for farm use near Highway 99 just north of Ashland

By Craig Breon for Ashland.news

The Medella Bison Ranch has the green light from Jackson County to begin installation of a 6-acre, 1.4 megawatt (MW) solar facility on land just outside Ashland’s city limits on the northwest side of town, after a county hearing officer issued a final decision approving the project, with conditions to protect the farmland on the site.

The final decision, issued Jan. 9, triggers a 21-day timeline for opponents of the project to appeal to the Oregon Land Use Board of Appeals (LUBA). Those opponents — primarily neighbors objecting to the visual impacts of the 84 pole-mounted solar arrays on gently sloping land directly adjacent to Highway 99 — are not expected to appeal.

The arrays will be mounted on 16-foot poles, with the roughly 26- by 30-foot photovoltaic panels extending above that by several feet, depending on the angle of the arrays towards the sun. The total electricity generated would be sufficient to power roughly 250 homes, depending on sun exposure and weather. Similar pole-mounted solar arrays can be seen across Highway 99 in front of car dealerships and Evergreen Federal Bank.

The ranch property for the arrays is zoned Exclusive Farm Use (EFU), a zoning type intended to preserve farm and ranchlands throughout Jackson County, with limited non-farm uses allowed. Solar generation, however, is specifically listed as a possible land use in EFU zones, under a conditional approval process.

The Medella Bison Ranch landowners, Thaddeus and Katie Gala, through their representatives, had asserted in application documents and at a Dec. 1 public hearing that the lands were not high-value farmland, had largely non-arable soils, and did not receive significant water from upslope due to the construction of Highway 99.

An artist rendering of a solar panel on a commercial-scale solar project on Medella Bison Ranch land near Ashland. A county official approved the project, clearing the way for construction. Screen grab

In response, county staff and project opponents cited decades-long use of the property for animal grazing and forage crop production. County staff also noted that EFU zoning for the land has provided the landowners with favorable property tax treatment for many years.

At December’s public hearing, the applicant cited additional evidence submitted to the county, arguing that construction and operation of the elevated solar facility would have little impact on future use of the land for farming and grazing purposes. Their claims included possible benefits to grazing animals from the shading solar arrays would provide.

An artist rendering of a solar panel set to go in at Medella Ranch, off Highway 99, outside of Ashland. Screen grab

Opponents of the project at the hearing focused not only on farmland preservation but also visual impacts to neighbors and to the northern “gateway” to Ashland along Highway 99. Residents above the project, including Daniel LosPalluto and Martin Eldridge, both homeowners on Ashland Mine Road who spoke at the hearing in opposition to the project, will essentially have a bird’s eye view of the solar panels as they look from their homes towards Grizzly Peak.

In her lengthy written decision, Hearing Officer Rebekah Dohrman found that the Medella Ranch project met the various standards required for a commercial-scale solar generation facility on EFU lands, so long as county staff recommended conditions are implemented.

The conditions imposed on the project include submission of a more detailed site plan, including setbacks and exact placing of the arrays, submission of a soil erosion plan, a restoration/revegetation plan and a limit on construction to occur only during the dry season, to reduce soil compaction.

The solar project will not be selling the power generated directly to Ashland’s electric utility.  The utility declined to purchase the power, “because it doesn’t make financial sense given the wholesale rate we pay to Bonneville,” according to an email sent from Ashland Mayor Tonya Graham to Gerry Lehrburger, a neighbor to Medella Ranch who organized opposition to the project. “It will be [the applicant’s] responsibility to install all of the infrastructure needed to bring that electricity into the City’s electrical grid.” 

Instead, according to city staff, the solar project will use “net metering” to sell power generated back to the utility grid.

A county parcel map shows one of the lots making up the Medella Bison Ranch marked in blue, an area including where the proposed solar panels would be installed along the east side of Highway 99.

Oregon’s net metering rules require utilities such as Pacific Power and the Bonneville Power Authority to credit residential and commercial customers for excess power sent to the grid. In general, the credits offset customers’ bills. In the case of a larger power provider such as Medella Ranch, the permitting required for selling power onto the grid is more complicated.

Timing will also be a factor for the Medella Ranch project. Under the federal “One Big Beautiful Bill” law signed in July 2025, commercial solar facilities must begin construction by July 4 to qualify for a 30% federal tax credit. 

Ashland.news has reached out to the owners of Medella Bison Ranch for further details on permitting and timing for the solar project but has not received a response as of this publication. This story will be updated when a response is received.

Email Jackson County resident, consultant and former environmental law instructor Craig Breon at ckbtravel@earthlink.net.

Related stories:

Medella Bison Ranch solar installation moves toward approval (Dec. 3, 2025)

Solar energy project on north side of Ashland goes to county hearing Monday (Nov. 28, 2025)

Picture of Steve Mitchell

Steve Mitchell

Related Posts...

Our Sponsors

Latest posts

Our Sponsors

Explore More...

The Ashland Independent Film Festival will spotlight homegrown talent Saturday, Feb. 21, during its revived Local Lens Spotlight at the Varsity Theatre. The one-night program features 13 short films by filmmakers from Jackson and Siskiyou counties, followed by a Q&A with the filmmakers and crew.
Ashland concertgoers have a chance to encounter a rare musical treat. Klezmer violinist Zoë Aqua and her Transylvanian String Band will play a house concert of klezmer music Wednesday, Feb. 25, as part of the group’s 12-show tour of the Western United States.
The Southern Oregon Chinese Cultural Association will bring some of the countries and customs of Asia together for the Lunar New Year celebration. Residents will have the opportunity to learn more about those cultures while kicking off the Year of the Fire Horse throughout downtown Jacksonville.
Ashland Outdoor School Ashland teacher and local fiddle instructor Robin Bliss-Wagner, critically injured Monday, is in a coma in the intensive care unit of a hospital as of publication time Wednesday. Area residents are working to raise up to $45,000 for his care, as well as to help with ICU and other expenses for his wife, Ruth, and their three sons.
Widespread accumulations of snow are expected Wednesday night into Thursday morning in Jackson County, according to a Wednesday afternoon update from the Medford office of the National Weather Service on a winter storm warning and winter weather advisory due to expire at 10 a.m. Thursday.

Don't Miss Our Top Stories

Get our newsletter delivered to your inbox three times a week.
It’s FREE and you can cancel anytime.

ashland.news logo

Subscribe to the newsletter and get local news sent directly to your inbox.

(It’s free)